Policy information sourced from City of London Local Plan

DM 2.1 Infrastructure Provision and Connection

  1. Developers will be required to demonstrate, in conjunction with utility providers, that there will be adequate utility infrastructure capacity, both on and off the site, to serve the development during construction and operation. Development should not lead to capacity or reliability problems in the surrounding area. Capacity projections must take account of climate change impacts which may influence future infrastructure demand.
  2. Utility infrastructure and connections must be designed into and integrated with the development wherever possible. As a minimum, developers should identify and plan for:
    • electricity supply to serve the construction phase and the intended use for the site, and identify, in conjunction with electricity providers, Temporary Building Supply (TBS) for the construction phase and the estimated load capacity of the building and the substations and routes for supply;
    • reasonable gas and water supply considering the need to conserve natural resources;
    • heating and cooling demand and the viability of its provision via decentralised energy (DE) networks. Designs must incorporate access to existing DE networks where feasible and viable;
    • telecommunications network demand, including wired and wireless infrastructure, planning for dual entry provision, where possible, through communal entry chambers and flexibility to address future technological improvements;
    • separate surface water and foul drainage requirements within the proposed building or site, including provision of Sustainable Drainage Systems (SuDS), rainwater harvesting and grey-water recycling, minimising discharge to the combined sewer network.
  3. In planning for utility infrastructure developers and utility providers must provide entry and connection points within the development which relate to the City’s established utility infrastructure networks, utilising pipe subway routes wherever feasible. Sharing of routes with other nearby developments and the provision of new pipe subway facilities adjacent to buildings will be encouraged.
  4. Infrastructure provision must be completed prior to occupation of the development. Where potential capacity problems are identified and no improvements are programmed by the utility company, the City Corporation will require the developer to facilitate appropriate improvements, which may require the provision of space within new developments for on-site infrastructure or off-site infrastructure upgrades.